WHAT ARE RENOVATION MINOR VARIATIONS?

The Building Act 2004 Section 45A enabled Building Consent Authorities (BCAs) the ability to grant minor variations during construction without having to go through the formal amendment process. In principle, this section was designed to provide time and cost savings for building owners, builders and the BCAs.

MINOR VARIATIONS

In 2009, the Building (Minor Variation) Regulations were created to provide (Building Consent Authorities) BCAs (Example; Auckland Council) with guidance on how to deal with these minor variations.

It also defined minor variations as being a minor modification, addition, or variation to a building consent that does not deviate significantly from the plans and specifications to which the building consent relates.

Examples given were:

  • Substituting comparable products such as substituting one internal lining for a similar internal lining.
  • Minor wall bracing changes.
  • Minor construction changes such as changing the framing method used around a window.
  • Changing a room layout such as moving the position of fixtures in a bathroom.

It also explained work which was not building work in respect of compliance with the building code such as kitchen joinery, skirting, built in shelving etc…

building contract jargon Minor variations

Design & Build Builders

In February 2010, the Department of Building and Housing (now Ministry of Business, Innovation and Employment), issued guidance on assessing minor variations which Auckland Council used as a basis in formulating their policy.

In each case, professional judgement is exercised by the council inspector onsite to assess each case on its merits. The policy allowed for flexibility to approve minor variations dependent on the council inspector’s technical knowledge and the time available during the inspection.

It has been reported that this system has been working very well on new build sites with significant time and cost savings resulting from it for both the owner and the council.

At this point, the council is still assessing jobs like this on a case by case basis. It is recommended that the following process be followed to avoid undue delays:

  • At pre-construction meetings or the earlier inspections, the definition of minor variation needs to be communicated including the process for applying. It should also be agreed that variations would be presented to the inspector as early as possible to avoid building them up and providing them in lump sums.
  • Minor variations must be assessed and approved before the work commences. In a lot of situations, the designer is asked to detail variations as soon as it has been identified yet the inspector does not know about it until weeks after this point. It would benefit all parties if the variation was communicated as the same time.
  • In some cases, multiple minor variations can add up to a substantial change in the building. In these situations, the inspector may require the variations to be processed as a formal amendment. Discussions should be held to establish what work can be continued while this is processed. Council processors would then be alerted to the urgency of the case and process these accordingly.

WHAT CONSTITUTES A VARIATION?

This is a frequently asked question. During building you might change your mind about something.

This might be at the suggestion of your builder or something you thought about later, for example, you might decide to install soundproofing between the bottom and second floor, or change the position of an internal wall.

Talk to your designer, project manager or builder to help decide if the variation is really necessary and how much it will cost.

It could require a new or amended building consent. Or it could turn out that it can’t be done anyway – it may be too far into the building process to start moving walls or inserting soundproofing products between floors. But you won’t know unless you ask.

Be aware that changing your mind is likely to cost you money – ask for at least an estimate in writing of the cost before you agree to the variation.

building contract jargon Minor variations
Minor variations

WHAT IS A MINOR VARIATION?

In 2009, the Building (Minor Variation) Regulations were created to provide BCAs (Building Consent Authorities i.e. Auckland Council) with guidance on how to deal with these minor variations. It also defined minor variations as being a minor modification, addition, or variation to a building consent that does not deviate significantly from the plans and specifications to which the building consent relates.

Examples of Minor Variations are:

  • Substituting comparable products such as substituting one internal lining for similar internal lining.
  • Minor wall bracing changes.
  • Minor construction changes such as changing framing method used around a window.
  • Changing a room layout such as moving position of fixtures in a bathroom.

If you want to know more about minor variations check out our Minor Variations article.

Whilst all information is considered to be true and correct at the date of publication, changes in circumstances after the time of publication may impact on the accuracy of the information. The information may change without notice and Style Plus is not in any way liable for the accuracy of any information printed and stored or in any way interpreted and used by a user.

Useful Building Contract Terms

We take a closer look at specific renovation or new build contract terms which may be confusing or misinterpreted when reviewing any building contract

Renovations Project Management

Whether you will undertake a small or large renovation, the need for renovations project management becomes an important factor in the success of a project.

Project Management

At Style Plus Renovations North Shore Auckland we see a project management plan as one potential pathway to a successful project outcome. There will always be factors, some unknown, that influence that plan. Issues, changes and variations typically will arise during a renovation, and we can only plan against so much risk. Therefore, the plan is as critical as the need to adjust it as we progress with the project

Building Contract Jargon

In this article, the team at Style Plus | Renovations | Auckland take a look at 4 building contract jargon terms, which is at best confusing or misinterpreted when reviewing the building contract.

Get started with a Free
Architects Renovation Feasibility Report

LET'S START

YOUR RENOVATION PROJECT

Tel us about your renovation project and we’ll call you back for a no-obligation chat about your ideas.

Alternatively, if you prefer, we can initially set up a meeting using Microsoft Teams or Zoom (and other meeting apps) for a no-obligation chat about your ideas.

We look forward to hearing from you to discuss your project and get you started on your renovation journey.

If you would like to know more about our renovation process, check it out here.

contact us
Upload Your File (1MB Max)

Additional Requests